Thursday, August 22, 2024

IRRIGATION ENGINEERING SHORT NOTES


INTRO & METHODS

  • Saline or Brackish water = 97.3%, Fresh = 2.7% , Total Water = 1.386 billion km³

  • Fresh water → Liquid form = 30%, Polar ice/glaciers = 70 %

  • Fresh water in india = 4% of the world's water resource

  • Sea water contain 80% of oxygen in freshwater  stream

  • Crop yield → Quintel/ha or tonnes/ha

  • 1 quintal = 100 kg, 1 ton = 1000kg 

  • Productivity → Crop yield/mm of water applied 

  • if water increases → Yield 1st increases then decreases

  • Tile drainage → Runs free gravity water that isn't directly available to the plants

  • Irrigable Land = 35% of Agriculture land ( world bank 2010)

  • Bhandara Irrigation scheme → Q=1.7LH1.5 m3/sec

  • Conjunctive use = Surface + Groundwater use

  • Consumptive use = Evaporation + Transpiration = Evapotranspiration

  • Perennial system → Constant + Continuous supply of water throughout crop period

  • Minimum depth of water required for safe and economical navigation = 2.70 meters

  • Surface drain → Design for storm run-off and surface flow resulting from excess irrigation

Type Of Irrigation Project.

  • Major > 10,000ha & > 5cr

  • Medium = 2k - 10k ha & 0.5 - 5cr

  • Small/minor < 2k ha & < 0.5cr

Types of irrigation

  • Mega is not a major irrigation method according to NRCS

  • Tile Drainage → Removes the free gravity water that is not directly available to the plants

  • Fertigation → process in drip irrigation to decrease evaporation

  • Sprinkler & drip are pressurised irrigation systems

i. Surface irrigation

  • Best for soil with low to moderate infiltration capacities. 

  • in India 75% irrigation by Surface irrigation

Flow irrigation

  • By gravity 

  • Ex → Flood/uncontrolled, perennial, canal irrigation, reservoir or tank irrigation, combined storage and diversion irrigation

  • Flood irrigation Soil kept submerged

  • Direct irrigation → River into main canal directly

Lift irrigation

  • By mechanical or manual means. ex well irrigation

ii. Sub-Surface (Capillarity) irrigation 

  • Suitable for highly permeable soil 

  • Has high efficiency

Methods of irrigation

Free/wild/uncontrolled

  • Rolling land (irregular Topography), Steep land

  • No control on flow by means of levees

  • Low efficiency

Inundation/Diversion


Border flooding

  • Land divided into no. of  strips

  • Time required to cover an area t=2.303.(y/f).log(Q/(Q-fA))

  • Max area that can be irrigated Amax=Q/f

  • f = Infiltration rate, y = depth, t = irrigation time require

  • Width = 10 - 20 m, Strip length = 100m- 300 m

Check flooding/Check basin flooding

  • Close growing crops-jowar paddy

  • Large Q ∴ for both permeable & less permeable soil

  • Water controlled by surrounding the area with low & flat levees

  • Cereal crops → Wheat, oat, barely

Basin flooding

  • Orchard trees, Special type of check flooding

Furrow or Corrugation

  • Crops are grown on ridges running on the side of the ditches

  • ⅕ to ½ land surface is wetted by water 

  • Aloo ki kheti yaad kar bas wahi hai

  • Depth of furrow = 20 -30 cm

  • Min furrow grade = 0.5%(1/2) to assure surface drainage

  • Raw crops → Sugarcane, sugar beet, groundnut, potatoes, tobacco

  • Furrow slope → Surface drainage ≥ 0.05% & Soil erosion ≥ 0.5%

Sprinkler irrigation/Overhead

  • Suitable → For land gradient is steep + Soil easily erodible (Uneven land surface,large undulation), Best for light soil, highly modulating land, Water is available with difficulty, land soil is excessively permeable or when soil is highly impermeable

  • Not suitable for soil (Clay) with low infiltration rate

  • Application rate → Limited by the infiltration capacity of the soil

  • Minimise erosion

  • 80% water application efficiency, minimum water wastage

  • Tea, Coffee, Not for Rice & Jute (for rice & Jute Standing water is used)

  • Limitations → Heavy initial investment & strong wind disturbs sprinkling.

Drip/Trickle/Micro/Localised Irrigation

  • Directly to the root zone

  • Arid condition in hot & windy Areas, low rainfall and strong winds, irregular topography

  • η = 80 - 90%.

  • Less loss(evaporation, percolation) → Very high Duty

  • Tomato, Corn, Fruit, Orchard of mango

SOIL-MOISTURE & PLANT

Saturated Soil

Gravitational water(Superfluous water)

Field Capacity

Capillary water (Available water) used by plant

Permanent Wilting Point

Hygroscopic (Unavailable water)

Dry soil

  • Superfluous water → Water which drains down so deep that plant roots cannot draw it

  • Zone of areatⁿ → Root soil water zone, intermediate zone & Capillary water zone

  • Saturation Capacity → Max water holding capacity of soil , replacing all air pores

  • Field Capacity(FC) → Water holding capacity of plant roots, or MC after free drainage has removed most of gravity water, depends on → porosity and capillary tension

  • Capillary water → used by plants

  • Height of capillary fringe = 1 - 1.5 meters

  • Top of the capillary zone lies above the water table at every point

  • Readily available moisture → Most easily extracted by plants (appx 75-80% of available water)

  • Permanent Wilting Point(PWP) →Water content below which plant can't extract water for its growth & it is a soil characteristic, moisture tension = 7 - 32 Atm

  • PWP moisture content → Represents hygroscopic(bonding) water

  • Hygroscopic water → Can't be extracted by plants

  • Soil-Moisture Deficiency → Water depth required to Bring moisture up to field capacity.

  • Meteoric water → Water derived from precipitation (Snow & rain), Lake, River

i. Equivalent depth of water held at FC

  • dw =(d/w)dFC

  • d = Root zone Depth

  • Porosity=(d/w)FC

ii. Available moisture or Storage Capacity of soil

  • dw' =(d/w)d[FC-PWP]

iii. Readily available moisture to plant  at OMC

  • =(d/w)d[FC-OMC]

iv. Readily available moisture at PWP

  • =(d/w)dPWP

Irrigation Water Quality

Sodium adsorption ratio

  • SAR =Na/(Ca+Mg)/2

  • 10-18-26

  • Low sodium water = 0 - 10 ← Suitable for all crops

  • Medium = 10 - 18

  • High = 18 - 26

  • Very high sodium water > 26 ← Unsuitable for irrigation

Sulphate(ppm)

  • Good water for irrigation = 0 - 192

  • Satisfactory irrigation = 192 - 400

  • Not suitable > 400 → Soil becomes infertile

Electrical Conductivity (EC)

  • Total Salt Concentration → Expressed as EC

  • Low salinity water = 100 - 250 → Suitable for all crops

  • Medium = 350 - 750 Micromhos/cm 

  • High  = 750 - 2250

  • Very High Salinity > 2250 → Unsuitable for irrigation

  • Salts of Sodium, Calcium, Magnesium , Potassium

WATER REQUIREMENT OF CROPS

  • With the increase in the quantity of water supply → Crops yield increases up to a certain limit and then decreases 

  • Mixed crop → To increase fertility of land

Command Area

  • Area over which canal irrigation water flows by gravity

  • Minor irri Project CCA < 2k ha 

  • Medium irri Project = 2k - 10k

  • High irri Project  ≥ 10k 

  • Salinity → ↑es infertility

Gross Command Area

  • Total area enclosed by an irrigation canal that can be included in an irrigation project for supplying water to agricultural land by a network of canals.

  • GCA = CCA + Uncultivable area

Culturable Command Area (CCA)

  • Area in which crops are grown at a particular time or crop season

  • CCA = GCA - Uncultivable area

Net Command Area

  • NCA = CCA - Area occupied by canals, Networks, ditches

Consumptive use 

  • Evaporation + Transpiration = Evapotranspiration

  • Measured  → Vol of water per unit area, Depth of water on irrigated area

  • Supplied partially by precipitation and partly by irrigation

Crop Type

  • Rabi(Winter) →oct-march, Wheat, Barley, Gram, Pea, Mustard.

  • Zaid march-june, Pumpkin, Cucumber, Watermelon, Bitter gourd.

  • Kharif (Monsoon) → june-sept, Paddy crop, Rice, jowar, bajra, Groundnut, jute, maze.

  • Water required Kharif = 2 - 3 x Rabi

  • Supplying water for R, K, Sugarcane → Capacity = max of i) R + Sugarcane or ii) K + Sugarcane

  • Cash Crop → Not used by farmers ex. jute tea sugarcane cotton tobacco, groundnut

  • Solid crop → Takes more than 4 months to mature

  • Crop Ratio = Area irrigated Rabi/kharif

  • Capacity of an irrigation tank depends on type of crop & duty

  • Crop period →  Showing to harvesting, Crop period > Base period

  • Base period → 1st watering at time of showing to last watering before harvesting

  • Paleo irrigation → Prior to sowing of crop

  • Kor watering → 1st watering plants grown few cm, Crops require max watering during kor watering, about three weeks after sowing

  • Kor period → Rabi crops = 4 weeks = 28 days

  • Water requirement → wheat < paddy

Duty

  • Area(ha) irrigated with 1cumec (1m³/sec) of water, Place of measurement of water

  • D=A/Q

  • Unit → hect/cumec

  • D↑es → Efficiency↑es

  • Humidity ↑es  → D ↑es

  • D ↓es → Supply ↑es

  • Duty is independent of Delta(∆)* → but by eqn D ∝ 1/∆

  • Duty is max at field & Minimum at barrage or weir

  • Full supply coefficient Duty on Capacity or no. of hectares irrigable per cumec of the canal capacity at its head.

  • Outlet discharge factor = Outlet factor = Area/Q outlet = Duty at watercourse = Duty at field = Duty at outlet

Delta 

  • Total depth of water Required/provided during base period (cm or m)

  • =8.64B/D

  • Where B = days, ∆ = m, D = ha/cumec

  • 1ha = 10⁴ m²

  • Vol of water from Q of 1cumec per day = 8.64ha.m = 86400 m³

  • → Well irrigation = 0.67 x Canal irrigation

  • Yearly intensity of irrigation = ioi1 + ioi2 + ioi3

  • irrigation frequency is function of Crop, Soil & Climate

  • kor depth → Rice = 19 cm, Wheat = 13.5cm, Sugarcane = 16.5cm 

  • Root zone → Rice = 90cm, Wheat = 30-40 cm 

  • Average ∆ → Rice = 120cm, sugarcane = 120cm, Tobacco = 75cm, Cotton = 50cm, Wheat = 40cm

  • Max base period = Sugarcane 

Frequency of irrigation

  • Foi is so decided when the average moisture content in the root zone of soil is at optimum moisture content which is near the wilting point

  • Irrigation frequency is a function of → Soil, Crop, Climate

  • Interval of water to be irrigated Guava fruit → Summer = 7-10 days, Winter = 15 days

Irrigation Efficiencies

  • Canal   Field Root Used

  • Conveyance = Q field/Q canal

  • Application = Qroot/Qfield

  • Used = Qused/Qfield

  • Storage = Qroot/Field Capacity

  • irrigation eff. = Qused/Qcannal

  • d =(1-y/d)100Water distribution efficiency

  • y =xi-d/n

  • d =xi / d

  • Crop water use efficiency = Yield of crop / Amount of water depleted by crop in evapotranspiration

Irrigation Requirement of Crop

  • Water requirement for crops = Consumptive use + Application loss + Special needs for land preparation + Transplantation loss

  • GIR > FIR > NIR > CIR

i Consumptive irrigation requirement(CIR)

  • irrigation water require to meet evapotranspiration needs of the crop during its full growth

  • CIR =Cu-Re 

  • Cu = Consumptive use, Re = Eff Rainfall

ii Net irrigation requirement 

  • NIR =CIR+LR+PSR+NWR

  • LR → Leaching requirements

  • PSR → Pre showing requirements

  • NWR → Nursery water requirements

iii Field irrigation requirement 

  • FIR=NIR/a

  • FIR = NIR + field application loss 

iv Gross irrigation requirement 

  • GIR=FIR/c

Design Discharge

  • Crops of diff season = max of all Q 

  • Crop of same season = Sum of all Q

  • Design Q = Q in field / (Time factor x Capacity factor)

  • Design Q is controlled by kharif crop

Consumptive use

Non consumptive use

→ irrigation

→ Fishing

→ Fire fight

→ City water supply

→ No Direct consumption of water

→ Hydroelectric power generation

→ Loss due to evaporation

→ in land navigation, pollution ctrl, Recreation use


CANAL DESIGN/IRRIGATION

  • Size of stone (d)  ≥ 11 RS ← for stable sedimentation in alluvial channel or remain at rest in a channel 

  • Critical tractive stress → The average shear stress acting on the bed of the channel at which the sediment particle just begins to move 

  • Unlined Canal τ = γw R S

  • Avg Shear stress on bed of a channel = γw R S = Critical shear stress

  • Avg Shear stress on bank of a channel = 0.75 γw R S = .75 x Critical shear stress

  • Avg  τ → bed/bank = 4/3 > 1

  • Capacity factor = Avg supply Q/ Full supply Q.

  • Balancing depth → Depth of cutting for which Area of cutting = Area of filling

  • Darcy eqn → Analysis of groundwater movement in alluvial soils

  • Silt charge → The weight of silt carried by the river per unit volume of water

  • The canal system & drainage system are complementary

  • Designed capacity of an irrigation channel is usually controlled by Kor demand of kharif crops

  • Order of preference → Depth > Slope > width → while aligning a canal

  • Revetment → A facing of dry stone pitching laid on sloping face of earth to maintain the slope in position or to protect it from erosion

  • Culvert are provided on road embankment in areas having no defined channel to carry surface runoff

  • Canal automation system → 1st practised in gujarat 

  • For design of major hydraulic structures on the canals → Khosla method of independent variables

  • Drainage density = Total channel length/Total drainage area

Types of canal

  • Rigid boundary canal → Designed on the basis of uniform flow

  • Most desirable alignment of an irrigation canal → Along the ridge line

  • Drains → Canals constructed for draining off water from waterlogged areas

Based on Canal Alignment

i. Ridge/Watershed Canal

  • Ridge/Watershed → The divide line b/w catchment area

  • Best alignment and Economical

  • Aligned along the ridge/natural watershed line → irrigate both sides of ridge 

  • Used in Plain Areas → Land slopes are relatively flat and uniform

  • Not intercept any natural drainage → No cross drainage work are required

ii. Contour Canal

  • Parallel to contours

  • irrigate only one side

  • Maximum cross drainage work required

  • Used in Hilly area

iii. Side slope

  • Perpendicular to contours

  • irrigate only one side

  • Flow → Parallel to natural drainage of country

  • Neither along watershed nor in valley

  • No cross drainage work are required

Nature of source supply

i. inundation canal

  • Non-perennial canal

  • Obtain their supplies through open cuts in bank of river which are called heads,Flow occurs only when there's a rise of flow in river

  • Carry water in only rainy season

  • To divert flood or excess water

ii. Permanent

  • Perennial & Non-perennial

  • Perennial canal → Flow throughout the year, Canals taking off from ice-fed perennial rivers

Based on Function

i. Feeder

  • Constructed to feed other canals

  • Feeding two or more canal or when main canal divided into two canals

  • ex. Indira Gandhi Canal, Lower chenab canal

ii. Carrier 

Based on Discharge

  • Canal system Head work → Main Canal → Branch Canal → Distributary → minor canal

  • Canal in form → Water course or Field channel

  • Main canal → Not to do direct irrigation

  • Branch canal → Q > 30m³/sec

  • Major distributary Q < 30 m³/sec

  • Minor distributary → Q < 2.5 m³/sec

  • Field channels or Watercourses → Small channel's excavated by cultivators in irrigation fields

Cross Section of irrigation canal

  • Sleep slope in cutting than feeling

  • Bank aim → To retain water

  • Service road → On canal for inspection purpose

  • Borrow pits → Central half width of the section of the canal

  • Pressure relief valves → Provided when canal is in full cutting

  • FSL of a canal at its head is kept 15 cm lower wrt parent channel

Freeboard 

  • Margin b/w FSL and Bank level

  • FB ensures that water does not overlap bank

  • Unlined canal = FSL to top of bank  

  • Lined canal = FSL to top of lining

  • IS 7112:1973 → Min FB = 0.50m (Q < 10cumec), = 0.75 (Q > 10cumec)

Discharge

Freeboard

1 - 5 cumec

5 - 10

10 - 30

30 - 150 

0.5 meter

0.6 m

0.75 m

0.90 m

Berm

  • Side of canal serve as road

  • Provided in all situation

  • ↑es factor of safety

  • Provided a scope for future widening of canal

Dowel

  • As a measure of safety in driving provided along the bank or on the service road

  • Helps in preventing slope erosion due to rain

Design of lined canal

  • Benefits → Helps increase the command area, Seepage reduction, prevent water logging

  • Earthen type lining → Compact earth lining, Soil cement lining

  • Hard surface lining → Cement concrete lining, Brick lining, Plastic lining, Boulder lining 

  • Thickness of Concrete lining → Governed by requirement of imperviousness and structural strength, Canal capacity, Nature of canal, Slope of bank of canal

  • A lined alluvial canal is best designed on the basis of Manning's formula

  • Life of concrete lining canal = 60 years

Most Economical section of Lined canal

  •  For Small Q (Q < 150m³/s) → Triangular section with circular bottom 

  •  For High/Large Q (Q > 150m³/s) → Trapezoidal section with rounded corners 

Lining max velocity

  • Cement concrete = 2 - 2.5m/s

  • Burnt clay tile ≤ 1.8m/s

  • Boulder ≤ 1.5m/s

Manning's formula

  • Best → Design of lined canal or lined  alluvial canal or impermeable soil 

  • V = (1/n) R2/3 S

  • n = manning's coefficient → L-1/3T

Design of stable channel

  • By → kennedy theory and lacey's theory

  • Theoretical concept of silt transportation is the same in both the theories

  • Lacey improved upon kennedy formula

KENNEDY THEORY 

  • Applicable to Irrigation channels only

  • Used the Kutter formula, Manning formula

  • RG Kennedy (EE pwd punjab) → 1895 → Upper bari doab canal system 

  • Vo =0.55my0.64

  • Vo → Maximum permissible velocity or critical velocity

  • Silt transportation power Qt ∝ Vo5/2

  • Section → Trapezoidal section

  • Recommended side slope → ½H : 1V

  • Kennedy found Upper bari doab canal → non silting non scouring

  • At critical velocity → non-silting and non-scouring

Garrett's diagram

  • Used by Kennedy to design Canals along longitudinal direction

  • Drawn for trapezoidal channel with slope 1/2H:1V

  • it gives graphical solution of kennedy’s eqn and kutter’s eqn

Critical velocity ratio (m) 

  • cvr  was introduce to take Silt grade effect in account

  • m = V/Vo = Actual mean velocity/Critical velocity

  • V > Vo (m > 1) ← Scouring

  • V < Vo (m < 1) ←  Silting

  • V = Vo (m = 1) ← No scouring, No silting

  • V=CRS= (1/n)R2/3S1/2

Value of chezy’s constant

  • Mannings C=R1/6/n Cn = R1/6 

  • Kutters → C = [1/n + (23 + 0.00155/S)] / [1 + (23 + 0.00155/S)x n/√R]

  • Bazin’s → 

  • Chezy’sC=V/RS 

Assumption of Kennedy theory

  • Silt is in suspension is due to eddy formed from the bottom/bed of the channel only

Limitations of Kennedy theory 

  • Eddies are generated from Base/Bed only

  • Depth is known

  • Trial & error based

  • No formula for side slope

  • No explanation for CVR

LACEY'S THEORY

  • independent eqn = 03, Regime condtⁿ  = 03

  • Applicable for both Alluvial rivers & Canal

  • Regime theory is applicable to channel in → True regime and Final regime

  • Silt supporting eddies → Generated from bottom as well as sides of channel

  • Wide & shallow w.r.t Kennedy theory

  • V = (Qf2/140)1/6=2fR/5

  • Regime (V) =10.8R2/3S1/3

  • Silt factor (f) =1.76d, d mm

  • R=5V2/2f=A/P V2=2fR/5

  • P=4.75Q 

  • S=f5/3/3340Q1/6

  • A = Q/ V

  • Regime Scour depth → Any river width =1.35(q2/f)1/3

  • Regime Scour depth → Alluvial regime width =0.473(Q/f)1/3 → Normal regime scour depth

  • Max flood Q V ∝ R2/3S1/3 → in a alluvial steam

  • General depth of scour calculated by lacey's formula in a river represents the depth below the maximum flood level in the river

Max scour depth

  • dmax = k x d

  • k → Nose of pier = 2

Ragoustiy coeff(N) 

  • Defined by Lacey 

  • N ∝ f1/4 =0.0225

  • Depends on Grade & density of boundary material

Lacey's Regime

  • Regime implies → Sediment comprises loose granular material

  • True Regime → Silt charge and Silt grade is constant, Discharge is constant, Flow is uniform, soil is incoherent alluvium

  • Final regime → Attains its section and longitudinal slope

  • Regime channel → No Scouring no silting

  • Permanent regime → Rigid boundary canals, Whose bed and banks are made with non-erodible material

Side slope in canal for different condition

  • For complete excavation → H : V = 1 : 1

  • For complete filling → H : V = 1.5 : 1

  • For partial filling → H : V = 1 : 1

CANAL REGULATION WORK

  • in barrages and canal head regulators → Weak and oscillating type hydraulic jump is formed

  • Capacity (Q) → Escape channel/ Parent channel > 50%

  • Compactness coefficient = P/2PA → P and A are Perimeter and area of drainage basin

  • Cistern → Designed on the downstream of a fall to dissipate the kinetic energy and prevent the damage to the bed and sides due to undesirable scour

Cross Regulator

  • in main canal increase the water head upstream when a main canal is running with low supplies

  • Head up water for adequate supply into the off-taking channel

  • Effectively controls the entire canal irrigation system

  • Absorbs fluctuations in various sections of the canal

Canal Head Regulator

  • Str at the head of canal @ 90 degree to the weir

  • Breast walls are provided with head regulator

Cross Drainage Work

  • At crossing of canal & natural drainage work

  • High flood drainage Discharge is small → Aquaduct or superpassage work

  • Fluming of canals → Contracting the waterway of the canal, reduces cost of cross drainage work

  • Syphon → Flow is under atmospheric pressure

1).Canal over Drainage

  • Aqueduct → HFL of drain much below bottom of canal

  • Syphon Aqueduct → FSL of D touches C bad, HFL of drain higher than canal bad flow under pressure through inverted syphon

  • Most severe condition of uplift on the floor occurs when canal runs dry and drain is at high flood level

2). Drainage over Canal

  • Super Passage → FSL of the canal is lower than drainage or stream

  • Canal Syphon → FSL of Canal touches D bad or FSL of canal higher than drain bed, flow is under pressure

3). Level Crossing

  • Canal water & drain water are allowed to intermingle with each other

  • Provided when canal & drainage approaches each other Practically at same level

Lift of material

i. Canal Drop/Fall 

  • Control of bed grade

  • Provided → Ground slope > Design bed slope → Available ground slopes steep than design bed slope of channel

  • Vertical drop fall → Drop ht ≤ 1.5m

  • Baffle/inglish fall → Drop ht > 5m

  • Canal fall is located most economically → Where depth of cutting < Balancing depth

  • Flumed fall length of body wall of fall < width of canal

  • Vertical drop fall (Sarda fall) Designed to minimise the depth of cutting, Used as meter fall, Ht ≤ 1.5 m, Rectangular crest (Q < 14 cumecs), Trapezoidal crest (Q > 14 cumecs), Neither draw-down nor heading up of water, Width of trapezoidal crest = 0.55 H+d , width of rectangular crest = 0.55 d

  • Ogee fall → Minimise the disturbance & water impact

  • inglis/Baffle fall → A straight glacis type fall with baffle platform and baffle wall

  • Montague type fall → Uses parabolic glacis for energy dissipation

  • Glacis type fall → The energy is dissipated due to hydraulic jump

  • Rapid fall → Sudden fall of level of ground along the alignment of a canal joined by an inclined bed

ii. Canal Escape

  • It is Safety values for the canals → Bypass excess water entering a canal

  • Full supply level, Remove Surplus water

  • Weir type escape → Crest = FSL of the canal

  • Regulator / Sluice type escape → Scouring off excess bed silt deposited

  • Escape → Purpose of washing some of canal’s water

iii. Canal Cross regulator

  • Control flow Depth

  • To head up water of adequate supply into the off-taking channel

iv. Canal Outlets or Module or Sluice

  • Ctrl Discharge

  • Canal outlet is a structure built at the head of a watercourse that is used to release water from a canal

Types of canal outlets

Non modular outlets

  • Q depend on difference of head b/w distributary and water course

  • Fluctuation both side → Q varies with either change in water level of distributary or that of water course

  • Ex. Drowned or Submerged pipe outlets, Masonry sluices, open sluice

Flexible/Semi-modular outlet

  • Pipe outlet discharging freely in the Atmosphere

  • It is an adjustable proportional module

  • Q = Function of Distributary as long as min working head available

  • Q increases with rise distributary level

  • Q unaffected by WL in water course

  • ex. Kennedy’s gauge outlet, Venturi flume, pipe outlet, open flume outlet,  

Rigid outlet/Modular outlets

  • Maintains Constant Discharge(Q) → No effect of fluctuations on any side

  • Q is independent of water level in distributors & watercourses 

  • Eg. Gibb’s rigid module, Drowned pipe outlet, masonry orifice

Criteria for judging performance of module

Efficiency

  • n = Head recovered/head put

Flexibility 

  • F=(dq/q)/(dQ/Q) = my/Hn

  • Proportional outlet F = 1 → Rigid or modular outlet

  • Sub Proportional outlet  < 1

  • Hyper proportional outlet > 1

  • Flexible/Semimodular outlet ≠ 0

Sensitivity 

  • S = (dq/q)/(dy/y)

  • Rigid module = 0

  • dq/q = Rate of change of discharge through outlet

  • dQ/Q = Rate of change of discharge through Distributary Channel 

  • dy/y = rate of change of water level through Distributary Channel 

Setting

  • S = m/n = H/y

  • Outlet → Q = KHm

  • Distributary → Q = Cyn

  • m → Outlet index, n → Channel index, y → Distribution depth

  • Wide trapezoidal channel → n = 5/3, m = 1/2(Orifice type outlet), m = 3/2 (Weir type outlet)

  • Triangular → m = 5/2

Blench Formula

  • X = 2Dc - D + (1/4)(HL - 3Dc/8)

DAM & RESERVOIR

  • Estimated avg life of a dam reservoir  = 75 years

  • Mass curve analysis → Determine live storage requirement for a reservoir

  • Sequent peak algorithm → Estimation of minimum Reservoir capacity needed to met given demand 

  • Usefulness of reservoir = Dead storage/Sediment deposition per year

  • Useful Storage → Water in reservoir b/w min pool level & Normal pool level

  • Useful/live storage → up to top level of sluice gate

  • Surcharge storage in Dam reservoir → Volume of water stored b/w FRL(full reservoir level) & MWL(Max water level)

  • Dead/inactive storage → Water stored in reservoir below the minimum pool level, provided to accommodate silt entry or sill-trapped in the reservoir

  • Dead storage is not provided in a dam of water resources project meant of irrigation and water supply

  • Valley storage → Vol of water held by natural river channel in its valley up to the top of its bank before construction of a reservoir

  • For flood control reservoir Effective storage = Useful + Surcharge - Valley storage

  • Sequent peak algorithm → Estimation of minimum reservoir capacity needed to meet a given demand

  • Free board → Difference b/w top of dam and max water level(MWL), governed by size of the reservoir, runoff, wind velocity

  • Depth of scour is normally measured from mean water level

  • Talus → A protection work at the downstream end of the weir in form of blocks of concrete or masonry 

  • Structure against overturning → Partial safety factor for dead load = 0.9

  • Inverted filter  → to prevent dams from failing by water piping, permeability increases in upward direction

  • Design yield of a storage reservoir < Firm yield

  • Economical height of a dam → Cost per unit of storage is minimum

  • Capacity-inflow ratio for a reservoir → Decreases with the time

  • Safety valve of a dam → Spillway

  • Retarding basin Dam reservoir not provided with gate controls on its spillway and other sluices

  • Ayacut → Area to be irrigated by a dam

  • Bank storage → increases the computed reservoir capacity in dam reservoir

  • Peak lag = Time for max inflow - Time for max outflow

  • Dam height increases → Cost per unit storage initially decreases and then increases

  • Water stop or Water bars → To prevent leakage through the transverse joints in a gravity dam

  • Overflow pipes → Provided at full reservoir level

  • Stilling basin → Provided at downstream floor to dissipate energy of flow

Mass curve method 

  • Storage capacity of a reservoir 

  • The demand line drawn from a ridge in the curve did not intersect the mass curve again → Represent the demand can’t be met by the inflow as the reservoir will not refill, 

Trap Efficiency

  • TE → Function of Capacity/inflow ratio

  • TE = Total sediment deposited in a given period/Total sediment inflow in that period

  • Measure of reservoir sedimentation

Types of reservoir

  • Storage reservoir → Design yield < Firm or safe yield

  • Linear reservoir → Storage varies linearly with Outflow rate

  • Multipurpose Reservoir → Planned and constructed to serve various purposes

  • Conservation reservoir → Retains excess supplies during periods of peak flows and release them gradually during low flows, Protect the area lying on down stream, Supply water in a city

  • Balancing reservoir → To address the frequent fluctuations in the rate of consumption

  • Retarding reservoir → No gates at outlet

  • FOS = Firm or safe yield / Design yield

Classification of Dam

  • Ghatghar (Lower) dam is a type of roller compacted concrete dam

  • Base width → Rockfill dam << Earthen dam

  • Check dam → Flood control

i. Based on Structural behaviour 

  • Gravity dam, Embankment dam, Arch dam, Buttress dam

  • Arch Dam → in a narrow V shaped gorge having sound and competent rock on side slope, idukki dam, Gorge Length < Height, Uplift on the base is not an important design factor

  • Buttress dam → Foundation pressure are less than gravity dam, it is a storage dam

  • Uplift pressure is of least importance in the designing of an arch dam

  • Concrete consumption → Constant angle arch dam < Constant radius arch dam

ii. Functional behaviour

  • Storage, Coffer, Diversion, Detention, Debris dam

  • Diversion dam → Used to raise the river water level to feed on off taking canal

  • Detention dam → To reduce flood peaks by impounding the flood flow excess of capacity of d/s channel

iii. Material of construction

  • Rigid, Non rigid dam

  • Rigid Dam → Arch, Timber, Steel

  • Non Rigid dam Rock fill, Earthen dam

  • Beaver dam → A type of timber dam

iv. Hydraulic design

  • Overflow, Non overflow dam

Zoned (Non homogeneous) Embankment type dam

  • Made up of more than one material

  • Central impervious core → Most suitable Clay mixed with fine sand

Gravity Dam 

  • Force exerted on it is resisted by its own weight

  • FOS → Sliding = 1.5 & Overturning = 2

  • Agg size ≤ 40mm (cement concrete dam)

  • Economic depth (Height) = Cost of dam per unit storage is minimum

  • Reservoir is full → Heel = Tension & Toe = Compression

  • Max ht. of masonry dam of triangular sectⁿ = b√Gs → b = base width, Gs = Specific gravity

  • Presence of tail water → Decreases Principal stress and shear stress

  • In extremely seismic zone acceleration due to EQ = 0.1 x g → for design of gravity dam

  • Narrow valley, fairly sound bedrock and stone masonry → favour a gravity dam

  • Bottom portion is stepped → in order to increase the shear strength of the base of the dam

Force acting on GD

  • Major resisting force → Self wt of dam

  • Main overturning force → Water pressure

i) Water pressure 

  • At water surface = 0

  • Base = γw H

ii) Uplift pressure

  • At heel = γw H

  • At Drainage gallery = γw h + ⅓ (γw H - γw h) = ⅔ rd of toe + ⅓ rd of heel

  • At toe = γw h

  • Control of uplift pressure → Constructing cutoff under upstream face, Drainage channels b/w the dam and its Foundation, Pressure grouting in foundation

  • Uplift force increases FOS against overturning

iii) Earthquake force

  • India → 4 Zones → II, III, IV, V

  • Zone V is the most serious zone

  • Hydrodynamic pressure due to EQ   =0.555KwH2  → at 4H/3π above base → opposite direction to acceleration imparted by EQ

  • Hydrodynamic pressure curve → Parabolic

  • Horizontal acceleration due to EQ → Results in Hydrodynamic pressure and inertia force(F = ma) into the body of the dam 

  • Vertical acceleration due to EQ → Vertical inertia force opp direction of acceleration

iv) Silt pressure

  • Ps=0.5Ka sub H2→ at H/3 from base

v) Wave pressure

  • Waves are generated on the reservoir surface bcz of wind blowing over it

  • Pressure distribution → Triangle of Ht = 5hw/3 

  • Total Pressure = =0.5whw2 → At 3hw/8 above the reservoir surface/max still water level

  • For wave action → ht. of free board = 1.5 hw and should not be < 0.9 m 

  • hw = Wave ht → depends on wind velocity and fetch

vi) ice pressure

vii) The weight of the dam

  • Major Resisting force

Principal stress

  • V =0 1=vSec2-2tan2

  • Considering EQ → 1=vSec2-(P +Pe)tan2

  • Empty reservoir → 1=vSec2

  • H =0 = (v-2)tan

  • Considering EQ → = (v-(2e)tan

Criteria of stability & Modes of failure GD

i) Overturning about toe

  • if Σ Fx > Σ Fy

  • Mr = Mo

ii) Compression or Crushing failure

iii) Tension failure

  • For no tension σ min = 0 → 1 - 6e/B = 0

  •  e ≤ B/6 → T = 0 (Middle third rule) → For no tension resultant force must pass through the middle third of Base

  •  e ≤ B/6 → Max CS/Max TS = ∞

iv) Failure due to Sliding

Elementary Profile of GD

  • Elementary profile of GD → Right angle triangle

  • Base width is used with some extension on the upstream side

  • Resultant force will shift Towards heel → by providing a top width for roadways and free board, for full reservoir condition

  • Base width = 65 % of dam height → No tension criteria and neglecting uplift pressure

Limiting/Maximum height For elementary Profile

  • H=f/w(G+1) → Uplift Pressure not considered

  • H=f/w(G+1-C) → Uplift Pressure considered

  • f = Allowable stress

  • Height of dam > H → High gravity dam

a) Empty reservoir 

  • Only Force due to Self wt is considered

  • Max compressive stress → At heel = 2W/B

  • At Toe → Zero stress

b) When reservoir is full

  • Max compressive stress/force → At the toe

  • Base width (B) = Max of [ H/G-C or H / (G-C)]

  • G = Specific gravity of dam material, C = Uplift coefficient, μ = Friction coefficient

i. For no Tension at base 

  • BH/G-C

  • Critical condition → When uplit is not considered → C = 0

  • Critical BH/G

ii. For no sliding

  • BH / (G-C)

  • Horizontal force < Foundation friction resistance → P < W

  • FOS = 1.4 

iii. For no overturning

  • BH/2(G-C)

  • Max stress at Toe = Pv = γw H (Gs -C)

  • Min stress at heel = Zero

  • FOS = 1.5

  • FOS ≤ W(b - x)/(Ph/3)

Earthen Dam

  • As compare to gravity dam earthen dam requires less skilled labour, can be constructed on almost every type of foundation

  • Most adverse condition for stability of slope for u/s face → Sudden Drawdown

  • Most adverse condition for stability of slope for d/s face → Steady seepage when reservoir is full

  • Earthen dam are best type of dam structure to resist EQ shocks

  • Upstream face of an earthen dam → an equi-potential line

  • Q > 10m³/s → Freeboard = 0.75m

  • Seepage ↑es → Comp.... in filling

  • Hydraulic failure of earth dam → Overtopping, Crushing, Sliding, toe erosion, wave erosion

  • Max instances of failure of earth dams take place → Due to over toppling due to insufficient spillway capacity

  • Riprap → To prevent the Sloughing of an earthen dam, sloughing is not a hydraulic failure

  • Stability analysis for the downstream slope of an earthen dam is essentially carried out for Full reservoir condition

  • In zoned rolled earth-fill dam the central core zone serves → the purpose of checking seepage loss from reservoir

  • Filter or Rock toe → Provided at downstream bund, To collect and drain out the seepage water, to prevent slogging of the toe due to the seepage flow and increase the stability of dam

  • Flow through an earth dam is an example of unconfined flow

  • Cut-off  → Reduces the uplift pressure in the base of the dam

  • Cut-off trenches for earth dam are effective → When the depth of pervious foundation strain below the dam is shallow 

  • If the design flood is underestimated earthen dam may fail → Due to erosion of upstream face

Embankment seepage ctrl in Earth Dam

  • Horizontal drainage filter, Toe filter, Protective filter d/s of toe, Chimney drain 

  • Focus of base parabola for dam having horizontal drainage filter → b from toe → b = width of Horizontal drainage filter

Foundation seepage ctrl in Earth Dam

  • Impervious cutoff, u/s impervious blanket, D/S Seepage berms, Drainage trench, Relief wall 

Back water curve

  • it is the profile of the rising water on the upstream side of the obstruction/dam

  • Rate of change of depth = 0 → back water curve to occur

Hydropower Station

  • Load factor = Avg load/Peak load

  • Capacity/Plant factor = Avg load output/installed capacity of plant

  • Utilisation factor = Water actually utilised for power/Water available in river

  • Design speed → Max efficiency

  • Headrace tunnel → a channel of free-flow tunnel leading water to the fore bay or a pressure tunnel leading the water to the surge tank

  • Penstock → carry water from storage reservoir to the power house

Hydel/Hydro-electric Scheme Classification

  • Low  head Scheme < 15m

  • Medium head = 15 - 70m

  • High head > 70 

  • Runoff river plants → A low head scheme, Suitable only on a perennial river

  • Pumped storage plants → Generates power only during the peak hours

Dams Projects 

  • Tehri dam → Highest(Tallest), Bhagirathi river (Uttarakhand)

  • Bhakra nangal dam → Concrete gravity dam, Largest dam in india, Satluj river (HP)

  • Hirakud dam → Longest dam, Reservoir for flood control, power and irrigation, Mahanadi()

  • Idukki → Non-overflow double curvature concrete arch, Periyar river(Kerala)

  • Rama-ganga → Uttarakhand

  • Sardar sarovar dam → concrete gravity dam, narmada river (Gujrat)

SPILLWAY

  • Spillway act as safety valves for the dam → Control excessive flood water

  • Provide str stability to Dam during reservoir flooding

  • Overflow Dam is also known as Spillway

  • Retarding basin → Provided with uncontrolled spillway & an uncontrolled orifice type sluiceway

  • Barrage & canal head regulators → Weak & oscillating type of jump formed

  • Reservoir with an uncontrolled spillway → The peak of plotted outflow hydrograph lies on the recession limb of the plotted inflow hydrograph

  • Solid roller bucket → Arranged at the end of a spillway to dissipate energy through hydraulic jump

  • When the outflow from a storage reservoir is uncontrolled as in a freely operating spillway the peak of outflow hydrograph → Occurs at the point of intersection of the inflow and outflow hydrographs

Chute spillways

  • The flow of water after spilling over the weir crest → At Right angle and parallel to weir crest

  • Flow → Supercritical

Side channel spillway

  • The flow of water after spilling over the weir crest → Parallel to weir crest

  • where long overflow crest required

  • where abutment are steep & control desired by narrow side Channel → High side and narrow gorge

Shaft spillway

  • In case of non availability of space due to topography → Shaft Spillway is most suitable

Ogee or Overflow spillway

  • Least suitable for Earthen dam

  • Mostly used with gravity Dam

  • minimise the disturbance & impact

  • Overflowing water is guided smoothly over the crest and profile of the spillway

  • Q=CLH3/2 → Q ∝ H3/2

  • Coeff of Discharge(C) depends on → Depth of approach, upstream slope, downstream apron interference, downstream submergence

  • Sharper crest → ↑es Cd & ↑es eff Head

  • Downstream curve → X1.85=-2yH0.85

  • Downstream profile with upstream face → Y/H= -0.5(X/Hd)1.85

  • Head of water < Design head → The coefficient of discharge < Design coeff of discharge

  • He = Hd → Cd = 2.2

Barrage type spillway

  • Used where a temporary and small storage above the crest is required

Gates

  • Fixed wheel gate → Most commonly used form of vertical lift gates on spillway crest

  • Radial gates → Least human/mechanical effort to operate

  • USBR drum gate → Can't be seen from a distance when lowered

  • Bear trap gate → for low navigator dam

Francis equation

  • Correction for end contraction for calculation of discharge capacity of spillway

  • Ln = Lt - 0.1n(hc + hv) → n = No. of deflecting corners

RIVER TRAINING WORK

  • River Training Work is generally required for meandering type of river

  • Width of launching apron = 1.5 depth of scour below original bed

  • Scour depth of protection works → D = yu/3 + 0.6

  • Rouse equation → Determining concentration of silt at any depth of river

  • Riprap → To protect river banks from erosion by river flow

Aim/Obj of RTW

  • To achieve ultimate Stability of river with the aid of river training

  • Safe passage  flood discharge

  • Efficient disposal of sediment load, preventing the river from changing its course, to protect river banks.

Types of RTW

  • High water training for Discharge (Q) → Flood control

  • Low water training for Depth (d) → Navigation purpose

  • Mean water training for Sediment → Preserve channel in good shape by efficient disposal of suspended and bed load

Method of River training 

  • RTW → Guide bunds, riverbank protection, marginal guidebunds , Groyne or Spur, bandalling etc.

  • Rtw for depth (to increase depth) → by Groyne/Spurs and Bandelling

  • Bandelling → locally bamboo made str used for the river course stabilisation by river bank erosion protection

  • Bunds → Temporary Spurs

  • Leeves → Parallel to river flow, Earthen embankments constructed parallel to river at some suitable distances for flood protection

Guide banks or Bell’s bund

  • To Channelize the flow of the river, to confine the width of river, Prevent outflanking of structure

  • Sweep angle → Upstream = 120° - 145°, Downstream = 45° - 60° degree

  • Min length → Upstream = 1.1L, Downstream = 0.1L- 0.25L → L  = length b/w abutments

  • Scour depth (D) → Nose = 2.25R, Transition from nose to straight = 1.5R, Straight reaches = 1.25R

  • Launching apron → Stone cover laid protect the face of the guide bank at river bed level

Groynes or Spurs or Dykes

  • Constructed Transverse to the river flow 

  • Most widely used river training works

  • Spacing = (2 - 2.5) x Spur length 

  • Function → Train river along a specified course by attracting, deflecting, repelling flow in river, protect river/canal bank by keeping the flow away from it, contract wide river channel, useful for improvement of depth

  • Spur are least effective in confining the flood water of alluvial rivers within reasonable waterway

  • Permeable spurs → River carrying heavy suspended load

Types of groynes

  • As per material of construction → Permeable and impermeable groynes

  • Permeable → Tree groynes, Pile groynes

  • As per height of groynes → non submerged groynes, submerged groynes

  • Attracting groynes → inclined towards downstream, θ = 45 - 60°C, not useful for bank protection

  • Repelling groynes → inclined towards upstream, θ = 60 - 80°C, Need strong protection directly subjected to current, protect upstream from scouring away

  • Deflecting groynes → Perpendicular to the bank, gives only local protection, relatively short length

  • Normal or Perpendicular groynes → vertically held

  • Sediment groynes → Permeable groynes, best for river carrying sediment, deposition of sediment carried by river without repelling/deflecting

  • Hockey groynes → with a Curved head

Types of river

  • Braided River → Two or more channel ex. Delta

  • Aggrading River → Silting rivers

  • Degrading River → Scouring, deficit of sediments

  • Ephemeral river → Flow for a short time after a rain strom and most of time their bed is dry

  • Meandering River → Erodibility of bed and banks of stream, Extra turbulence Generated by the excess of river sediment during floods, generally occurs in its through  stage

  • A meander increase the river length but a cut-off reduces the river length

  • Tortuosity = Curved length/Direct axial length of river or Curved length/Meander belt > 1

  • Meander ratio = Meander belt/meander length

  • Meander pattern of river → Developed by Dominant discharge

  • Dominant Q = ½ - ⅓ of Qmax

  • Length of meander = 53.61Q

  • Width of meander = 153.42Q

  • Width of meander belt = Transverse distance b/w Apex point of one curve and the apex point of the next reverse curve

  • When a river starts meandering the sediment carrying capacity first decreases and ultimately increases

  • Deepest river portions will be available at the outer edges of meander loop

  • River bend in alluvial soil → Scouring on concave side, Silting on convex side

  • Dendritic → The pattern which involves irregular branching of tributary stream in many directions and at almost angle in the drainage basin

  • Juvenile Stage → River flow along an undulating topography and the gradient is very high

DIVERSION HEADWORK

  • Storage headwork → Dam, constructed to store water

  • Diversion headwork → To rise water level & divert to canal constructed across river and at head of offtaking canal

  • The most suitable location for canal headwork → The Trough stage (alluvial stage) of the river

  • A canal headwork in rocky stage of a river is not suitable → A costly head regulator is required, more falls are necessary to dissipate the energy, more cross drainage works are required

  • IS : 6004 - 1980 → Design of sediment ejector for irrigation and power channels

  • Suspended silt concentration in a channel carrying silt load → Higher at bottom layer than upper layers

  • Most commonly used vertical lift gates in modern day → Fixed wheel gates

  • For Smooth entry → Angle B/W head regulator and water/weir/barrage = 90 - 110 Degrees

Components of Diversion Headwork

  • Retrogression of downstream levels, generally considered in the design of weir or barrage → Higher at low water levels stage than at high flood stage

  • Effective control of silt energy into canal, the sill of the head regulator should be above the sill of the under sluice

  • If there are two canals taking off from each flank of a river → There will be two divide wall and two under-sluice

  • Devices used to reduce the silt entry into offtaking channel → King’s vanes, Gibb’s groyne wall, curved wings, desilting basins, vortex tube, cantilever skimming platform

  • Gibbs groyne wall → Denied entry of Bed load of the river into canal

Canal Head Regulator

  • Str at the head of canal @ 90 degree to the weir → Regulate supply of canal

  • Control entry of silt into canal, Completely exclude high flood entering into canal

  • Consist of no of spans separated by pier 

  • Breast walls are provided with head regulator

  • The crest of a scouring sluice = 1.2 meter below the crest of a head regulator

Weir

  • To raise water level and divert to offtaking canal

  • Gravity weir → Wt of weir = Uplift pressure caused by head of water seeping below weir

  • Non gravity weir → Wt of concrete slab + wt of divide piers keeps the structure safe against uplift

  • Length of weir proper → Trought age > Boulder stage

Barrage

  • Function is same to that of weir → raise water level and divert to offtaking canal

  • The provision of a series of gates across the river for flow regulation

  • Crest level is kept at low level

  • In alluvial reach of river → Scour depth = 2 x lacey's scour depth

  • Downstream sheet piles → Provided to control failure due to piping by high value of exit gradient

Sluice gate

  • Removing excess sediment from entering the canal at its head regulator

  • Crest of under Sluice Portion of weir is kept at  lower level then crest of Normal Portion and ponding is done by means of gates

Undersluice or Scouring sluice 

  • Helps in removing silt near head regulator

  • Opening provided in weir wall with crest at low level

  • The crest level of the under sluice bays are kept at avg bed level of the river

Silt excluders 

  • On River Bed  & u/s of head regulator or front of head regulator

  • Exclude silt from entering into the canal

Silt ejector/extractor

  • On Canal bed & d/s of head regulator

  • Remove silt which already enters into canal

Divide wall or divide Groynes 

  • Separate undersluices from the main weir → Provided Right angle to the axis of weir

  • Creating a still poll, To control silt energy into channel, To form still water pocket in front of canal head

  • can be designed as cantilever retaining wall subjected to silt pressure and water pressure from undersluice side

Fish ladder

  • Enable Fish to move freely and safely in the river

  • To check velocity flow in fish ladder Baffles or staggering device are provided

  • V = 3 - 3.5 m/sec

WATER LOGGING

  • in Loose saturated Sand

  • Capillary fringe reaches root zone of plant → Root zone become saturated

  • Drainage by gravity stops

  • Leads to → ↓es Temp, ↓es Crop yield, Soil become Alkaline, Growth of weeds, Accumulation of salt, defective air circulation in root zone

  • WL → Mild slope > Steep slope, Long rooted plants > Small rooted, Marshy area > Swamp

  • Lift irrigation → Preferable type of irrigation in water logged area, Reclaim a water logged area

  • Spacing of tile drain ∝ Coeff of permeability of the soil to be drained

  • Weeds in surface drains → Increases the value of coeff of rugosity

  • Drain → Canal Constructed for draining of water from WL areas

  • Water logged soils are infertile → Due to lack of aeration and reduced soil temperature

  • Vadose water → Water occurring in zone of aeration

  • Spacing of drain tile L =4K(b2-a2)/q

Cause of WL

  • Excess rainfall

  • High water table

  • Seepage of canal

  • High Irrigation & frequent Irrigation

  • Flooding of field

  • Note → Excess tapping of groundwater is not responsible for Water Logging

Water logging control

  • ↓es by providing Drains

  • Lining of canals is used to control water logging in Agricultural land.

  • reducing intensity of irrigation

  • Intercepting drains

  • Crop-rotation

  • Adopting consumptive use of surface & Subsurface water

Reclaimanation

  • Uncultivable land is made fit for cultivation

  • Alkaline soil → Gypsum + leaching

  • Acidic soil → Limestone as a soil amendment

  • Mulching → ↑es infiltration & ↓es evaporation by spreading of material on soil

  • Leachate → Generated from liquid present in Landfill

  • Leaching → Remove salinity (soluble salts) of the soil by downwards movement of water through the soil

  • Eutrophication → Plant Nutrition Accumulation, Excessive discharge of nutrients in water bodies

Bligh's Creep Theory

  • Design of Hydraulic structure on Permeable strata

  • t=FOS H/(G-1) = 4H/3(G-1) → Thickness of floor

  • Head loss = Hydraulic gradient x Creep length

  • Assumption → Equal weightage to horizontal and vertical creep → No distinction made b/w horizontal and vertical creep

  • Bligh's coff of creep C = 1/exit gradient

  • C = 18 ← Light sand & mud

  • Width of Launching Apron = 1.5 x D → D = scour depth below original bed

  • Creep length = B + 2(d1+d2+d3..) → B = horizontal floor length, d1,d2,d3 = pile lengths

Khosla's theory

  • Design of weir & barrages on permeable foundation 

  • Exit gradient = H/d =H/Creep length

  • =(1+1+2 )/2

  • α = b/d

  • Exit gradient depends upon b/d, H/d ratio

  • Exit gradient ∝ Exit length → Horizontal length of apron is based on permissible exit gradient

  • ie ∝ Denseness of downstream cutoff

  • Exit gradient → in absence of downstream cutoff = infinity

  • Critical exit gradient depends on depth of upstream and downstream sheet

  • The Undermining or piping or sand boiling of the floor starts from the Tail end

  • Safety against piping failure Lrqr ≥ CH

  • Upstream pressure on upstream floor → By Bligh’s theory < Khosla’s theory

  • To increase inflow of water to Sub Surface water reservoir → Natural drainage of the area is improved

  • Pressure distribution under weir floors are based on conformal transformation of potential flow into the W plane

  • Critical hydraulic gradient → Stability of str against seepage pressure = 1.0, Alluvial soil = 1.0

  • Cut-off walls beneath a hydraulic structure reduces the exit gradient

  • For long range run off → Losses are function of temperature

Khosla’s safe exit

  • Silt(Shingle) = 0.25 - 0.20

  • Coarse sand = 0.20 - 0.17

  • Fine sand = 0.17 - 0.14

No comments:

Post a Comment

'Winners don't do different things. They do things differently' - Shiv Khera

Popular Posts